We at SEC are happy to supply the electrical service to your location as well as install the meter in your facility within 30 days of payment as long as the safety standards are satisfied and no outstanding payments are owed. You can track the status of your request via (Website/electric application).
To get the service:
1/ Submit a service delivery request through the company's website, Baladi platform, or MODON platform.
2 / Check all the required requirements.
3/ Along with the building permit, obtain a "Coordination Certificate" stating that an electrical service can be delivered and showing the location of your meters, the amount of building loads, the number of your units, the capacity of the breakers, and the size and sizes of the cables.
Your type of establishment is residential or commercial. If you want to apply for a new receipt, make sure of the following:
1 / Obtain the building permit for your site.
2 / Perform the thermal insulation of construction in sites where this is required.
3 / Prepare the installation site of your meter(s), according to the technical requirements of the company mentioned in the coordination certificate.
4 / Complete the earthing system..
Breaker Capacity (KVA) More than | Breaker Capacity (KVA) To | Service Connection Cost (SAR/KAV) |
---|---|---|
1 | 30 | 60 |
30 | 60 | 95 |
60 | 120 | 120 |
120 | 500 | 175 |
500 | 4000 | 250 |